DENVER – (PR
Newswire) – January 13, 2003 – Gasco Energy,
Inc. (OTCBB: GASE) today provided an interim operations
update on wells in its Riverbend Project in Utah’s
Uinta Basin, and its Wyoming Projects in the Greater
Green River Basin. Operations, including drilling
and completion activities, continue to ramp up on
Gasco’s acreage. With the upgrades in pipeline
compression planned for Utah and the completion of
several gathering projects in Wyoming, Gasco expects
to see an increase in production volumes in the coming
weeks and months.
Commenting on recent developments, Gasco CEO and President,
Mark Erickson said, “A lot has been accomplished
since our last operations update. In Utah, we have
completed the drilling of two wells described in our
last update, new completion techniques are being explored
and the unforeseen compression problem has been resolved.
“Seasonal demand for Rockies natural gas is
reducing the basis differential,” Erickson continued.
“As a result, prices received at Opal, Wyoming
are currently $2.80 – $3.10 MMBtu. We expect
to see higher prices during the winter with some softening
during the shoulder months of March, April and May
of this year. Prices are anticipated to rebound with
the completion of the Kern River Pipeline expansion
that is scheduled for an on-time completion during
the second quarter of this year. The additional takeaway
capacity that this pipeline will provide is expected
to significantly reduce the gas-on-gas competition
that contributed to last summer’s large basis
differentials.”
Utah Operations Overview
Gasco has run casing on its second well of the fall
program which reached a total depth of 11,900 feet
on December 1, 2002. To alleviate gathering system
constraints associated with inadequate pipeline compressor
capacity, Gasco and the system operator have agreed
to put a new compressor in place increasing the capacity
up to 6.5 million cubic feet (MMcf) daily. The BLM
has approved the necessary permits for total compression
capacity up to 7.0 MMcf daily. The gas-gathering contract
for the new compressor has been signed by the operator,
and the compressor will be installed within the next
three weeks.
Utah Well Updates
Federal 23-29 (Gasco-operated; Gasco 25% working interest
[WI]) – This well reached a shortened total
depth of 10,660 feet in March 2002 and encountered
52 feet of net Wasatch pay and 89 feet of net Mesaverde
pay. All Wasatch and Mesaverde intervals are now completed.
Efficient engineering techniques allowed Gasco to
complete three separate frac stages in one day in
the Wasatch Formation. Current production of 250 –
300 thousand cubic feet of natural gas per day (Mcfd)
and 3.5 barrels of condensate per day is restricted
by the compression restraints. The well should produce
approximately 1,500 Mcfd once the aforementioned additional
compression capacity is added
Federal 42-29 (Gasco-operated; Gasco approximately
40% WI) – This well reached total depth of 11,770
feet in May 2002 and encountered 75 feet of net Wasatch
pay and 275 feet of net pay in the deeper Mesaverde
Formation. The two lowest Mesaverde fracture stages,
located between 10,936 feet and 11,499 feet, were
completed in one day using Halliburton’s flow-thru
frac-plug technology. Production, which is estimated
to be 1.0 MMcfd or greater based on initial flow tests
late last summer, has been shut in due to compression
constraints, which will be addressed by the new compressor
described above. Gasco and Halliburton plan to frac
two more stages and then turn the well to sales with
five stages remaining.
Federal 23-21 (Gasco-operated; Gasco 50% minimum WI)
– This well reached total depth of 11,746 feet
in October 2002. The 23-21 encountered 32 feet of
net pay in the Wasatch Formation and 220 feet of net
pay in the Mesaverde Formation and is currently awaiting
completion. The 23-21 will earn the remaining interest
that Gasco does not own within the Mesaverde Formation
on a 320-acre block.
Lytham Federal 22-22 (Gasco-operated; Gasco 50% minimum
WI) – This well has had casing run and cemented
after reaching a total depth of 11,900 feet on December
1, 2002. This well began flaring gas in the Wasatch
at 7,200 feet and showed well in the Mesaverde. The
Wasatch Formation has 55 – 70 feet and the Mesaverde
Formation has more than 200 feet of net pay. The 22-22
will earn the remaining interest that Gasco does not
own within the Mesaverde Formation on a 320-acre block.
Federal 32-31 (Gasco-operated, Gasco 50% minimum WI)
– This well has been spudded with a small rig
which has been moved off the drill site. Conductor
casing has been set. Projected total depth is 11,500
feet. Gasco’s final working interests will be
determined once the completion programs are designed
for the 23-21, the 22-22, and the 32-31, respectively.
Federal 23-12 (ConocoPhillips-operated: Gasco 20%
WI) – This well reached total depth of 11,810
feet in July 2002 and encountered 127 feet of net
pay in the Mesaverde Formation. This well was completed
using more modern techniques and sold gas immediately
to sales. This well is currently producing at a stabilized
rate of 650 Mcfd, 2-3 barrels of oil per day and 50
barrels of water per day.
Federal 43-24 (ConocoPhillips-operated; 20% Gasco
WI) – This well reached a total depth of 11,474
feet and is awaiting completion.
Wyoming Projects Overview
Burlington has been aggressively drilling in the Muddy
Creek project area having recently completed drilling
on their fourth test. Including Gasco’s Piney
10-16 well drilled in 2001, there are now five wells
in the project area. Additionally, Burlington has
completed shooting 120 miles of additional high-resolution
2-D seismic. This data has been processed and is currently
being interpreted by Gasco and Burlington geoscientists.
Gasco has acquired 100 square miles of 3-D seismic
in the Grindstone project area. Processing on this
shoot is anticipated to be complete within the second
quarter. Wells are currently planned for drilling
on lands adjacent and contiguous to the Gasco leasehold
by Encana and Williams. Williams also recently completed
the 25-mile 10” Merna pipeline which crosses
much of Gasco’s leasehold position and should
allow for close and easy future well connections.
It is not anticipated that many additional wells will
be drilled in Wyoming until winter lease stipulations
are lifted this spring. The production from the existing
wells will be monitored until that time.
Wyoming Well Updates
Grindstone Butte 41-8 (Burlington-operated; Burlington
100% WI) – The well reached a total depth of
13,200 feet in January 2002. This well was completed
in multiple over-pressured zones and is awaiting pipeline
hook-up. No additional information has been released
as Burlington is keeping this well a “tight
hole.”
Muddy Creek 33-27 (Burlington-operated; Burlington
100% WI) – This well reached a total depth of
9,350 feet. The well is currently completed and was
recently tied to a sales line. Monthly production
volumes from the Lance Formation have ranged from
1.4 MMcf to 5.0 MMcf while Burlington has been bringing
this well on line. Burlington eventually plans to
commingle production from the Lance and Mesaverde
formations.
Muddy Creek 13-3 (Burlington-operated; Gasco 35% WI)
– This well reached total depth of 9,460 feet
in October 2002. This well encountered 80 –
100 net feet of pay and was testing at rates of 650
Mcfd to 750 Mcfd and 25 to 30 barrels of water per
day before it was turned to sales.
Muddy Creek 24-14 (Burlington-operated; Gasco 0% non-consent)
This well reached a total depth of 9,570 feet in September
2002. It is completed and has just begun producing
to sales.
Gamma Ray 11-25 (Burlington-operated; Burlington 100%
WI) – This well reached a total depth of 13,000
feet in October 2002. It provides Burlington the right
to earn an additional 640 acres from Gasco. A completion
was made in a Lance interval at approximately 10,800
feet.
CD Federal 14-4 (Burlington-operated; Gasco 35% WI)
– This well reached a total depth of 10,870
feet in October 2002 and casing was run. The 14-4
will earn the participants additional farmout acreage
totaling 21,000 gross acres from an unrelated third
party. The well is complete and recently began flowing
into a pipeline.
Piney 10-16 (Gasco-operated; Gasco 100% WI) –
This well reached total depth of 9,230 feet in April
2001. The well was completed in one Lance gas sand
for a rate of 250 Mcfd. Gasco engineers are designing
a completion program to add additional production
from this wellbore (approximately 75 - 80 more feet
of pay). This well is a two-mile offset to Burlington’s
Muddy Creek 33-27.
2-D seismic shoot – Burlington recently completed
shooting 120 miles of high-resolution 2-D. The recent
shoot increases the Company’s total 2-D to more
than 200 miles. The Company’s geoscientists
are currently analyzing the data from the shoot.
3-D seismic shoot – Gasco is financially participating
in a 3-D seismic program that will cover a large part
of its Grindstone project and some of the Muddy Creek
project. Gasco purchased 100 square miles of the 250
square mile shoot and all of the data is currently
being processed.
About Gasco Energy
Gasco Energy, Inc. is a Denver-based natural gas and
oil exploitation and development company that focuses
on natural-gas-rich prospects in the Rocky Mountain
area of the United States. The Company currently is
active in the Uinta Basin in Utah and in the Greater
Green River Basin of Wyoming. To learn more, visit
www.gascoenergy.com.
Forward-looking statements
Certain statements set forth in this press release
relate to management’s future plans, objectives
and expectations. Such statements are forward-looking
within the meanings of Section 27A of the Securities
Act of 1933, as amended, and Section 21E of the Securities
Exchange Act of 1934, as amended. All statements other
than statements of historical facts included in this
press release, including, without limitation, statements
regarding the Company’s future financial position,
potential resources, business strategy, budgets, projected
costs and plans and objectives of management for future
operations, are forward-looking statements. In addition,
forward-looking statements generally can be identified
by the use of forward-looking terminology such as
“may,” “will,” “expect,”
“intend,” “project,” “estimate,”
“anticipate,” “believe,” or
“continue” or the negative thereof or
similar terminology. Although any forward-looking
statements contained in this press release are to
the knowledge or in the judgment of the officers and
directors of the Company, believed to be reasonable,
there can be no assurances that any of these expectations
will prove correct or that any of the actions that
are planned will be taken. Forward-looking statements
involve known and unknown risks and uncertainties
that may cause the Company’s actual performance
and financial results in future periods to differ
materially from any projection, estimate or forecasted
result. Some of the key factors that may cause actual
results to vary from those the Company expects include
inherent uncertainties in interpreting engineering
and reserve or production data; operating hazards;
delays or cancellations of drilling operations because
of weather and other natural and economic forces;
fluctuations in oil and natural gas prices in response
to changes in supply; competition from other companies
with greater resources; environmental and other government
regulations; defects in title to properties; increases
in the Company’s cost of borrowing or inability
or unavailability of capital resources to fund capital
expenditures; and other risks described under “Risk
Factors” in Part I, Item 1 of the Company’s
latest Annual Report on Form 10-K filed with the Securities
and Exchange Commission.